Oracle Apps Inventory – Build a Workday Calendar with Exceptions
Build a Workday Calendar with Exceptions
Overview
In this practice you will build a workday calendar with exceptions.
Assumptions
- Replace XX with your terminal number or initials.
- You must have access to an Oracle Application Vision database or comparable training or test instance at your site on which to complete this practice.
Tasks
Define a Workday Exception Set
1. Responsibility = Inventory, Vision Operations
2. Navigate to the Exception Templates window.
-
(N) Setup > Organizations > Calendar Exception Templates. Complete template details
- Name = XX-Except
- Description = Exception set for team XX calendar
- Name = XX-Except
4. Enter at least 3 exception dates. Note: Don’t forget to select the Days On checkbox!
Define a Workday Calendar
Use the Define Workday Calendar feature to define a workday calendar for your team. You will define a calendar workday pattern, exceptions to that pattern and build your calendar.
5. Navigate to the Workday Calendar window
- (N) Setup > Organizations > Calendars
6. Create a workday calendar
- Name = XX-Cal
- Description = Calendar for team XX
- Quarterly Type = 4/4/5 Week Pattern
- Calendar Date Ranges = First Monday in January of the current year to the default.
7. Define a workday pattern according to the following table:
Seq |
On |
Off |
Description |
1 |
5 |
2 |
Regular work week |
8. Close the Workday Patterns window
Verify your Calendar
9. (B) Dates. Note: You should see the days of your work week blacked out.
Load your Exception List
10. Load your Exception List
- Load From = Template
- Template = XX-Except
Note that your exceptions are added to your workday calendar.
Build your Workday Calendar
11. Submit the concurrent request to build your workday calendar
- (M) Tools > Build
12. Record your request number __________________ .
Verify the Concurrent Request Completes Successfully
13. Navigate to the Requests window and verify the request completed successfully.
Answer the Following Questions about your Calendar
14. Record the following information regarding your workday calendar.
Question |
Answer |
What was your workday pattern? |
|
Which days are designated as off days |
|
How did you identify the off days? |
|
Take a look at another month in which you designated exceptions to your workday calendar. What days have designated exceptions? |
|
Close windows until you are back at the Navigator. |
Solution – Build a Workday Calendar with Exceptions
Define a Workday Exception Set
1. Responsibility = Inventory, Vision Operations
2. Navigate to the Exception Templates window
- (N) Setup > Organizations > Calendar Exception Templates
3. Complete template details
- Name = XX-Except
- Description = Exception set for team XX calendar
4. Enter at least 3 exception dates
Note: Remember to select the Days On check box!
Define a Workday Calendar
Use the Define Workday Calendar feature to define a workday calendar for your team. You will define a calendar workday pattern, exceptions to that pattern, and build your calendar.
5. Navigate to the Workday Calendar window
- (N) Setup > Organizations > Calendars
6. Create a workday calendar
- Name = XX-Cal
- Description = Calendar for team XX
- Quarterly Type = 4/4/5 Week Pattern
- Calendar Date Ranges = First Monday in January of the current year to the default.
7. Save
8. (B) Workday Pattern
9. Define a workday pattern according to the following table:
Seq |
On |
Off |
Description |
1 |
5 |
2 |
Regular work week |
10. Save
11. Close the Workday Patterns window
Verify your Calendar
12. (B) Dates
Note: You should see the days of your work week blacked out.
Load your Exception List
13. (B) Exception List
14. (B) Load
- Load From = Template
- Template = XX-Except
15. (B) OK
16. (B) OK
17. Note that your exceptions are added to your workday calendar.
Build your Workday Calendar
18. Submit the concurrent request to build your workday calendar
-
(M) Tools > Build
19. Record your request number __________________.
20. (B) OK
Verify the Concurrent Request Completes Successfully
21. Navigate to the Requests window
-
(M) View > Requests
- Specific Requests = Selected
- Request ID = Your request number
- Specific Requests = Selected
22. (B) Find
23. Verify the request completed successfully.
Answer the Following Questions about your Calendar
24. Record the following information regarding your workday calendar.
Question |
Answer |
What was your workday pattern? |
|
Which days are designated as “off” days |
|
How did you identify the “off” days? |
|
Take a look at another month in which you designated exceptions to your workday calendar. What days have designated exceptions? |
|
Close windows until you are back at the Navigator. |